Charlie Miller Jun 6, 2013

Dear Charlie

As programed, this week we started some works at site, please take a look at the pictures, you will see two teams:

1) First team is working with wood, they are making new frames to hold the concrete of 13, 14, 15 and 16 th floors

2) Second team is working of the reinforcement of the structure under the subfloors -3 and -2, this is necessary because we need to hold a huge weight because of the construction elevators that will be located at that part. The construction elevators will be needed in all this second phase to carry all the interior materials such as blocks, tiles, doors, pipes, equipment, etc. and for workers and engineers too.

Next week I will send you some more advances about the project.

Best Regards,

Mdi. Esteban Fiallo Reyes

GERENTE GENERAL

EFIAG CONSTRUCTORA S.C.C.