Charlie Miller Jul 7, 2013

Dear Charlie:

· As planned this Monday we place the concrete at the 16th floor (or 12th counting from main) and next week we will have ready the 17th floor to do the same thing.

· This days we have been working on the main floor preparing all the walls of this place,

· Walls of the for subfloors # -3,-2 and -1, are almost ready!!!

· The elevators are finally ready for use, this will be a good help for the rest.

Everything is doing good!!

Mdi. Esteban Fiallo Reyes

GERENTE GENERAL